01 NCAC 30J .0305 CONSTRUCTION MANAGER-AT-RISK SELECTION FOR OTHER THAN UNC SYSTEM PROJECTS
(a) Upon receipt of a letter from the capital projects coordinator listing three firms in priority order along with recommendations and selection information, the secretary of the SBC, upon determination that all information has been submitted, shall place the request for consideration on the agenda for the next SBC meeting.
(b) The capital projects coordinator shall make a report to the SBC outlining the procedures that were followed and justification for the priority list of three firms. Upon a determination by the SBC that the rules in this Subchapter have been followed, the SBC shall:
(1) Affirm the selection of the firms in the priority order recommended by the agency; or
(2) Select the firms in a different priority order from that recommended by the funded agency and give justification for such selection; or
(3) Request a new priority list and give justification for such request.
History Note: Authority G.S. 143-135.26;
Temporary Adoption Eff. February 1, 2003;
Eff. March 1, 2004;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.